Many seismic retrofits on the West Coast are required by work the owner initiates: a new roof, a tenant improvement, a change of use. Others are required by city programs with fixed deadlines. Knowing which applies to a building, and when, lets an owner plan the work on their own schedule.
How seismic retrofit requirements are triggered
- Mandatory programs. A city identifies a class of vulnerable buildings, issues orders to comply, and sets deadlines. Los Angeles has run programs of this kind since 2015.
- Passive triggers. Requirements in the existing building code that apply when an owner pulls a permit, reroofs, increases occupancy, or changes use. Seattle and Portland rely primarily on these today.
Passive triggers cause the most surprises because they surface mid-project, after the budget and schedule are set. The sections below summarize the current requirements in Seattle, Portland, and Los Angeles.
Seattle URM retrofit requirements
Seattle has no mandatory URM retrofit ordinance yet. For unreinforced masonry buildings, the Seattle Existing Building Code (SEBC) sets four passive triggers.
- Any permit: parapets. The Seattle Department of Construction and Inspections (SDCI) requires abatement of unbraced URM parapets and other unsafe appendages, such as URM chimneys, as part of any construction or mechanical permit submitted for plan review (SEBC 302.9 and A113.6). Final approval is held until a parapet permit is submitted.
- Reroofing. A reroof that replaces 25 percent or more of the roof area requires parapet bracing (SEBC 706.3.1).
- Occupant load increase. A significant increase over the legally established occupant load requires a retrofit. SDCI weighs both the size of the increase and the occupancy type. In SDCI’s own example, a nightclub going from 500 to 625 occupants qualifies; a retail store going from 30 to 45 does not.
- Substantial alteration. A major renovation, reoccupying a vacant building, or a change to a higher-hazard occupancy can classify a project as a substantial alteration. That requires seismic retrofit along with other current life safety and energy code upgrades.
A voluntary seismic retrofit does not by itself trigger a substantial alteration.
What is coming. Resolution 32033 (2021) directs the City toward a mandatory URM program. The proposed deadlines run 7 years from adoption for critical buildings (schools and emergency facilities), 10 years for high-vulnerability buildings, and 13 years for all others. The City has said it will not adopt a mandate until funding and support for owners are identified. Since November 2024, the 2021 SEBC lets owners have a completed retrofit recognized in the City’s URM database, including through the reduced-scope Alternate Method for qualifying buildings.
Portland seismic upgrade triggers (Chapter 24.85)
Portland City Code Chapter 24.85 governs seismic requirements for existing buildings. Its triggers apply only when a building permit is applied for, and several are specific to URM bearing wall buildings.
- Reroofing a URM building (24.85.065 A). Replacing a roof covering after removing more than 50 percent of the roof area within a five-year period requires wall anchorage at the roof and parapet bracing to meet the ASCE 41 standard for existing buildings (BPOE).
- Alteration or repair cost on a URM building (24.85.065 B). When permitted alteration or repair costs in a two-year period exceed a per-square-foot threshold, the entire building must be upgraded to ASCE 41-BPOE. The thresholds differ for single-story and multistory buildings and are adjusted each year for construction costs, so confirm the current figure with the City before scoping work.
- Change of occupancy (24.85.040). A change to a higher-hazard occupancy affecting more than one-third of the building’s net floor area, or adding 150 or more occupants, requires a seismic upgrade of the whole building. Increases are counted cumulatively against the building’s legal occupancy as of October 1, 2004.
- Live/work conversion. Converting a URM bearing wall building to live/work space requires an ASCE 41-BPOE upgrade regardless of construction cost.
What is coming. Starting January 1, 2029, any permitted alteration valued above a base of $175,000, indexed annually since 2004, will require an ASCE 41 seismic evaluation (24.85.060). Buildings permitted to seismic standards after January 1, 1974, and small single-story light-frame buildings are exempt.
Portland also offers practical relief: permit fees for seismic strengthening work are waived below $2,500 and reduced by half above that, and the City can approve a phased upgrade program of up to ten years under a recorded agreement.
Los Angeles mandatory retrofit: soft-story and non-ductile concrete
Los Angeles requires retrofits of two building types by deadline, under Ordinance 183893, signed in October 2015. The Department of Building and Safety (LADBS) issues an order to comply, and the clock starts from that order.
| Building type | Description | Deadlines from order |
|---|---|---|
| Wood-frame soft-story | Older multistory wood-frame buildings with weak or open ground floors, such as tuck-under parking or storefront openings | 7 years to complete construction |
| Non-ductile concrete | Older reinforced concrete buildings lacking the ductile detailing required in later codes | 3 years to submit a checklist, 10 years to submit plans, 25 years to complete construction |
The soft-story program is well underway. The concrete program is at an earlier stage: as of February 2024, LADBS reported that 6 percent of roughly 1,200 non-ductile concrete buildings had met the construction milestone, with citywide completion due around 2041. These are large, expensive projects, and owners who begin engineering early have more control over cost and timing.
Other Southern California cities, including Santa Monica, Pasadena, and Beverly Hills, run their own programs with different criteria. A building’s address determines which rules apply. LADBS provides a search tool for checking whether a specific building has an order to comply.
How to plan for a seismic retrofit trigger
The common thread across all three cities is timing. A trigger found during permit review arrives with a fixed scope and a project schedule already committed. A trigger identified in advance can be designed, priced, and sequenced with the rest of the work.
- Before acquisition. Check the building’s status in the Seattle URM database or the LADBS retrofit search; in Portland, request the City’s URM list directly. Confirm the construction type. Budget for any work a buyer’s planned renovation is likely to trigger. A pre-acquisition engineering and PML review can identify these costs before closing.
- Before a reroof. Brace parapets and install roof-level wall anchors before or alongside the new roof. Bracing after the roof is complete means reopening finished work.
- Before a tenant improvement or change of use. Confirm the occupant load and occupancy classification against the thresholds above. In Portland, alteration costs accumulate over a two-year window, so several modest projects can add up to a full-building trigger.
- When a mandate is likely. Phasing work over several years, where a city allows it, spreads cost and keeps the building occupied.
Compliance with a city timeline also has limits as a risk strategy. SDCI notes that California building owners have been held liable for URM failures despite meeting local retrofit deadlines.
Frequently asked questions
Does reroofing trigger a seismic retrofit in Seattle?
For URM buildings, yes. Any construction permit requires bracing of unbraced URM parapets, and a reroof covering 25 percent or more of the roof area requires parapet bracing under SEBC 706.3.1.
Is seismic retrofit mandatory in Seattle?
Seattle has not yet adopted a mandatory URM retrofit ordinance. Retrofit is required when a project triggers it through a permit, an occupant load increase, or a substantial alteration. The City’s proposed mandatory program would set deadlines of 7 to 13 years after adoption, depending on the building’s vulnerability classification.
What triggers a seismic upgrade in Portland?
Under Portland City Code Chapter 24.85, a change to a higher-hazard occupancy affecting more than one-third of the floor area, or an increase of 150 or more occupants, triggers an upgrade. URM bearing wall buildings are also triggered by a roof replacement covering more than 50 percent of the roof within five years, or by permitted alteration costs above a per-square-foot threshold within two years. Starting January 1, 2029, larger alterations will require an ASCE 41 seismic evaluation.
What are the Los Angeles soft-story and non-ductile concrete deadlines?
Under Ordinance 183893, owners of wood-frame soft-story buildings have 7 years from the order to comply to complete construction. Owners of non-ductile concrete buildings have 3 years to submit a checklist, 10 years to submit plans, and 25 years to complete construction.
How do I find out whether my building is on a retrofit list?
Seattle publishes its URM database online (search here), and LADBS offers a search tool for its retrofit programs. In Portland, we would be happy to check that out for you.
If you have a reroof, renovation, acquisition, or change of use ahead, we can review the building and identify which requirements apply before the project is scoped. Contact us to schedule an assessment.
Sources
- SDCI Tip 345: Seattle Existing Building Code Requirements for URM Buildings (Aug 2025)
- SDCI: URM Frequently Asked Questions
- SDCI: URM Program Timeline
- Portland City Code Chapter 24.85
- Portland Permitting & Development: Commercial Structures (cost triggers, May 2025)
- LADBS: Non-Ductile Concrete Retrofit Program Status (Feb 2024)
- Buildings.com: Earthquake Retrofits Mandated for Los Angeles Facilities (Oct 2015)
- NBC Los Angeles: How to check if your building needs retrofitting